September 20 (SeeNews) - Slovenia's sole nuclear power plant Krsko produced 485,974 MWh of electricity net in August, 2% below plan, the plant operator said.
Gross electricity output totalled 516,209 MWh in August, Krsko said in a statement posted on its website.
A total of 6.7 cubic metres of low and intermediate-level radioactive waste was stored in August, Krsko said.
Krsko NPP, located in Slovenia near the border with Croatia, generates some 40% of Slovenia's electricity output. It operates a Westinghouse pressurised light water reactor of 2,000 MW thermal power capacity.